WOODLAWN STORAGE
Preliminary Cost Estimate
August 28 2008
EXCAVATION $50,000.00
FOUNDATION $175,000.00
BASEMENT SLAB $108,000.00
STEEL $1,315,000.00
CONCRETE FLOORS 100,000 SQ. FEET $500,000.00
LABOR $655,000.00
SPRINKLERS $229,000.00
PLUMBING $20,000.00
ELECTRICAL $650,000.00
ALARM SYSTEMS $220,000.00
BRICK $37,500.00
STUCCO $68,000.00
EXTERIOR DOORS & WINDOWS $2,500.00
ASTHETIC ARCHITECTURAL EXTERIOR STEEL $30,000.00
LANDSCAPE SPRINKLER SYSTEM $50,000.00
ELEVATORS $240,000.00
SITE DEVELOPMENT $424,000.00
ENGINEERING/SURVEYING $45,000.00
WATER FEES $100,000.00
SEWER $30,000.00
BUILDING PERMIT $150,000.00
CONTINGENCY $250,000.00
SALES TAX $470,000.00
$5,819,000.00