WOODLAWN STORAGE |
|
|
|
|
Preliminary Cost Estimate |
|
|
|
|
August 28 2008 |
|
|
|
|
|
|
|
|
|
EXCAVATION |
|
$50,000.00 |
|
|
FOUNDATION |
|
$175,000.00 |
|
|
BASEMENT SLAB |
|
$108,000.00 |
|
|
STEEL |
|
$1,315,000.00 |
|
|
CONCRETE FLOORS |
100,000 SQ. FEET |
$500,000.00 |
|
|
LABOR |
|
$655,000.00 |
|
|
SPRINKLERS |
|
$229,000.00 |
|
|
PLUMBING |
|
$20,000.00 |
|
|
ELECTRICAL |
|
$650,000.00 |
|
|
ALARM SYSTEMS |
|
$220,000.00 |
|
|
BRICK |
|
$37,500.00 |
|
|
STUCCO |
|
$68,000.00 |
|
|
EXTERIOR DOORS & WINDOWS |
|
$2,500.00 |
|
|
ASTHETIC ARCHITECTURAL EXTERIOR STEEL |
|
$30,000.00 |
|
|
LANDSCAPE SPRINKLER SYSTEM |
|
$50,000.00 |
|
|
ELEVATORS |
|
$240,000.00 |
|
|
SITE DEVELOPMENT |
|
$424,000.00 |
|
|
ENGINEERING/SURVEYING |
|
$45,000.00 |
|
|
WATER FEES |
|
$100,000.00 |
|
|
SEWER |
|
$30,000.00 |
|
|
BUILDING PERMIT |
|
$150,000.00 |
|
|
CONTINGENCY |
|
$250,000.00 |
|
|
SALES TAX |
|
$470,000.00 |
|
|
|
|
$5,819,000.00
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|